Enighed not soon come

enighed2To no one’s surprise, the V.I. Port Authority said the $16 million Enighed Pond Freight Terminal Project “may” open next spring; not within 30 days as was confidently predicted several weeks ago. Delays caused by the stench produced from dredging and failure to find a place to dump that sediment are among the factors being blamed, according the Virgin Islands Daily News. The update on Enighed was announced at this week’s Authority governing board meeting.

Port Authority executive director Darlan Brin said the Public Works department has given permission for the dredged material, stacked up along the shores of the Pond, to be taken to the Susannaberg landfill. The transfers have begun. Meanwhile, back at the pond, dredging has resumed and could take two more months, the newspaper report said.